Issue Management Methodology for Tracking Project Issues
1. What is an Issue? An issue is an incident, circumstance, problem or inquiry that affects or potentially affects the timely delivery of the project, product or service, it may also impact the quality of deliverables and the cost of production. Some projects are ongoing and the definition of an issue is a little different. A help desk defines an issue as a request for help that requires a response. A service department keeps track of service requests as issues. A software maintenance group tracks reports of software bugs and enhancement requests as issues. Because of the impact issues have on a project, product development or ongoing service, issue management is an important aspect in any management methodology. This issue management methodology promises to make the handling of issues a seamless part of your larger scoped methodologies rather than a process separate from them. It is usually not hard for team members to identify issues, but it is still worth having a working definition of an issue. Remember that the more ambitious your project the more issues will arise. Action item: The project team must be made aware of what issues are, provide some examples, and ask other team members to provide some examples. 2. Requirements A central repository of issue information easily accessible to all team members, because it is good for team morale and productivity to know that their issues are being addressed. An automated central repository like Issue Tracker is desirable because it make the issue management and reporting much easier. Action item: Choose a central repository for your issues. An issue manager is the person chosen to oversee all issues. It can be the project manager, team leader or another person in a responsible leadership position. The issue manager is responsible for making sure that there is consistent, disciplined and continuous progress made on all issues. The issue manager is accountable to upper management for the progress made on all issues. The issue manager communicates issue progress to the team, upper management and all stakeholders. Action item: Appoint an Issue Manager and notify the issue manager of their role and responsibilities. This issue management methodology represents best practice for managing issues. However, the goal is to have a successful project, product development or service, the goal is not to follow a methodology fanatically. Action item: Adapt the methodology so your project's success is maximized. 3. Steps 3.1 Discovery Issues can arise at any time. When an issue is discovered it is recorded in the central repository. It is important to allow issues to be recorded by a broad group of people including team members, upper management, users, customers, stakeholders, vendors and contractors. It is important because if there are barriers to reporting an issue then there is an increased chance that the issue will go unrecorded. You cannot address issues that you do not know about. It is not necessary that everyone has access to central repository, but the more you can allow the better. Action item: Set up access to the central repository for those people that need it. 3.2 Recording Training people to identify issues is often unnecessary, however getting people to record the issue in the central repository will take some training and encouragement. For example, a team member may mention an unrecorded issue to the project manager during a coffee break or other informal occasion, this team member needs some encouragement to record such issues in the central repository. For all kinds of issues, prevention is better than correction. Also, issues tend to be less severe if they are addressed earlier rather than later. This means that every effort should be made to report issues as soon as they are discovered, instead of waiting for the issue to become "serious enough" before recording it. Do not be afraid of duplicating an issue or overlapping with existing issues, it is better than missing an issue. A complete description of the cause of the issue should be recorded in the central repository. Resist the temptation to describe the issue in terms of a solution. Any implication of the issue should be recorded. Attach any supporting documentation, screenshots, report output, faxes, error messages and other media that describes the issue. The person who is recording the issue can make a recommendation for a solution, if they have one. This person should also assign the issue if possible, even if it is only assigned to the issue manager for re-assignment. When an issue is initially recorded it should be recorded in the central repository with a status code that reflects the fact that it is new issue and has not been reviewed. An attempt should also be made to categorize and rank the severity of the issue. The date and who created the issue should be recorded in the central repository. This is done automatically for you in systems like Issue Tracker. Many teams describe issues in terms of the desired solution, leaving others to deduce the actual issue. This is not best practice since it limits the scope of possible creative solutions. As an example a badly worded issue: "We need more people." There is no indication in this example of what the issue actually is, so finding alternative solutions is impossible. If the example issue had been worded as "The shipping department has swamped us with product, there is a possibility of spoilage if we cannot get the product delivered." With the issue worded this way perhaps the shipping department can become aware of how there actions are causing issues down the line and adapt their actions. 3.3 Initial Review The initial review is a triage of new issues. It is usually performed by the issue manager or deputies who are familiar with the scope and priorities of the project. If the team is small the entire team can meet for the review. For each new issue the status, category and severity are reviewed and the issue assigned to someone for action and optionally an owner is identified as follows. Sometimes the same person who records the issue may be doing the initial review, so these two steps can be fused into one in this situation. 3.3.1 Issue Status A decision is made about the next state of the issue. (The previous state was "new".) The next status of the issue reflects the nature and timing of the action to address the issue. It is one of the following:
3.3.2 Categorize the issue A first attempt at categorizing the issue was made when it was first recorded. But, now during the initial review the category can be refined. The proper issue category is helpful when prioritizing the resources required to address issues. It is especially useful for reporting purposes. Action item: Discuss with the team how best to categorize the issues you expect to get, and document the categories that will be used. 3.3.3 Rank the issue severity The severity reflects the importance of getting the issue resolved. Obviously, you want to direct resources at the most important issues before the lesser ones. Action item: Choose a small set of severity codes that have a clear ranking. For example: Trivial, Standard, Important, Critical. Some people prefer: Low, Medium, High, Very High. 3.3.4 Assignment From the start, the next person to take action on the issue must be assigned to the issue and notified. Issue Tracker will automatically notify the person assigned to the issue via email. If the issue description is incomplete, the issue can be assigned to the appropriate party to gather the information necessary to make the issue description clear. Assign a person and not a group. Experience has shown that assigning issues to individuals leads to greater accountability than assigning issues to groups. An individual can be confronted about lack of progress, it is much harder to confront a group of people. A group can be represented by a group leader, so you can assign an issue to the group leader who will take action to reassign the issue to correct group member who will actually address the issue. 3.3.5 Ownership It should be possible to decide which stakeholder is the owner of the issue. Having an issue owner is a way of recording who is accountable for the issue's resolution. Owners must review the issues they own for progress to resolution. If the progress is not sufficient the issue manager should be told so that the situation can be remedied. 3.4 Taking Action The process to address an issue iterates over the following sub-steps until the issue is resolved.
Notice that the action taken may involve reassigning the issue, changing status, refining the issue description, changing the category of the issue. All of these changes should be recorded in the central repository. Changing of status, category and severity are automatically logged for you in an automated system like Issue Tracker. 3.5 Ongoing Oversight Consistent and continuous evaluation of issues by the issue manager and the team must take place to bring the issues to resolution. This can take place through a periodic review of all active issues in the central repository with the team and a separate review with the stakeholders. Escalate issues as needed by re-assigning or by changing issue ownership. Report and communicate progress on all issues to upper management and to the team, subscriptions can be used by upper management and the team to follow progress on individual issues. This reporting can be integrated into project status reporting. Analyze issue progress and adapt actions. The central repository should be able to provide feedback on how efficiently the issues are proceeding from creation to resolution. If it is taking too long to resolve important issues, then the issue manager must find ways to improve the turn-around time. 4. Finally The following are a few further action items Action item: Distribute copies of this issue management methodology to team members and stakeholders so that everyone knows how and why issues are managed. Action item: Adapt and scale this issue management methodology to suit you project's scale and quirks. Action item: Create your central repository, and get started today. This issue management methodology has evolved over many years. It evolved from experience on projects with budgets from $500,000 to $50,000,000 which had a total number of issues ranging from a few hundred issues to many thousands. In half the cases the project team was physically dispersed in several countries. Grant Murray is project manager and enterprise application architect specializing in technical project leadership strategy. Email Grant Murray for questions or comments regarding this article, or if you require project management consulting.
MORE RESOURCES:
Google News |
RELATED ARTICLES
Mantra for Managers What do organizations look for in a prospective employee with special reference to fresh MBA graduates? The two key assets that an organization looks for is the potential of the individual and ability to pursue his goals in all situations. Every organization expects its team of fresh recruitees to grow into top quality Managers and therefore it is very important to evaluate the potential of the fresh graduate. Tales From the Corporate Frontlines:The Importance of a Competitive Wage and Benefit Package This article relates to the Compensation and Benefits competency, commonly evaluated in employee satisfaction surveys. It tells the story of a company that needed to attract new employees and discovered how a competitive wage and benefits package was integral to this process. Give Yourself a Boss Day Gift, Part 2: Are You the Position or the Person? Are you the position or the person?Bosses can lose their own identity sometimes. It's easy. What We Have Here Is A Failure To Communicate Today's successful organizations are the ones which carry on open and honest communications with their employees. If employees know and understand the mission, they will help communicate it to customers. Meetings: Don't Just Show Up, Stand Out and Shine Meetings, whether they're regularly scheduled routines in your company or now-and-then get-togethers, can be a place for you to gain positive visibility and to showcase your capabilities. Here are three strategies that will help you stand out and shine. Business Fails When We Do Not Talk You may remember being told as a child, "Keep quiet!" "Children should be seen, not heard," and "You talk too much." You were a "good" kid if you kept quiet. The Challenges of Human Resource Management IntroductionThe role of the Human Resource Manager is evolving with the change in competitive market environment and the realization that Human Resource Management must play a more strategic role in the success of an organization. Organizations that do not put their emphasis on attracting and retaining talents may find themselves in dire consequences, as their competitors may be outplaying them in the strategic employment of their human resources. Counseling Interviews for the Marginal Employee ACTIVE LISTENING: The most frequent cause of failure in therapeutic counseling interviews is the interviewer's tendency to talk too much. Numerous studies have shown that in counseling interviews the average manager will talk as much as 85 percent of the time. Ten Business Reasons Why Asking for Help Works In fact, bringing your people - any of them - into your confidence and asking for help, is a very powerful tool indeed. The form of words' "I need your help", works best. Using Employee Opinions Effectively When Designing HR Programs Using Employee Opinions Effectively When Designing HR ProgramsEmployee opinion is one of the most powerful resources available to human resource professionals. But what are the best methods for harnessing those opinions?Conversation - Welcoming feedback via informal conversation is the first step towards utilizing the viewpoints of employees. Five Steps to Better Employee Management Hiring employees is a huge responsibility. Before hiring anyone, be sure to carefully analyze your needs in terms of extra assistance. Which ITIL Process Should We Implement First? The following question is usually debated a lot amongst IT managers. "With which process should we start when implementing ITIL?" Everybody has their own views, but here are my takes on it. Small Business Outsourcing: An Introduction Outsourcing is the delegation of a business process to an external service provider. The service provider will then be responsible for the day-to-day running and maintenance of the delegated process. The Few & the Many: Free Trade, Outsourcing, & Communication Have you noticed that some sound ideas get bad publicity? Two I have in mind are outsourcing and free trade.No doubt you could name others, but looking at these two initiatives helps us understand a communication challenge for many companies and not-for-profit organizations. Business Innovation - Organizational Culture Creativity can be defined as problem identification and idea generation whilst innovation can be defined as idea selection, development and commercialisation.There are other useful definitions in this field, for example, creativity can be defined as consisting of a number of ideas, a number of diverse ideas and a number of novel ideas. Rethinking the CEO-Chairman Split Traditionally, in American businesses, the same person occupies the role of chairman of the board and chief executive officer, though this is gradually shifting to the European model. In most European, British, and Canadian businesses, the roles are usually split, in an effort to ensure better governance of the company, and in turn bring higher returns to investors. The 6 Steps to Six Sigma Step 1Get the proper level of Six Sigma expertise at the executive level of the company. If the top leaders don't understand the advanced six sigma principles, the company has no shot to attain total quality. Business Knowledge Management In the last few years a lot has been written about Business Process Management, and about technologies supporting it such as BPMS, SOAP and Web Services. Most of these theories, tools and techniques refer to processes of a highly structured nature. Internal Control - The Why and How Many retailers do not have good internal controls in place and place little importance on them. They are concerned with the buying and selling of merchandise and do not place enough emphasis on making certain that the sales get recorded, the money gets in the bank, the invoices are paid only once and the inventory reports are correct. Internal Communication: 12 Essential Elements There are 12 essential elements of a successful internal communications strategy:1. Effective employee-directed communications must be led from the top Effective communications require the active commitment and endorsement of senior managers. |
| home | site map |
| © 2006 |